Email Updates

Here's your weekly construction update. Have a fun and safe Labor Day weekend!

Howard Avenue and Independence Street:

Construction crews will not be working Friday, August 31 or Monday, September 3.

Week of September 3rd Schedule*-

  • Monday (September 3) - The construction crew will not be working.
  • Tuesday & Wednesday (September 4 & 5) - The contractor will be working on sanitary sewer on Howard north of Independence Street.
  • Thursday & Friday (September 6 & 7)- The contractor will start working on watermain on Howard Ave. They are going to start at Main St. E. and work their way north similar to the sanitary sewer

*Due to the rain this past week, crews will be working on items from last week during the first part of the week.


Parkview Road and Maple Ridge Drive:

No additional updates at this time.

Construction Contacts- New Construction Supervisor:

Adam has left his position with Stantec for another opportunity. Tanner is his replacement.

For any non-emergency type questions or concerns, please feel free to contact City Engineering staff using the information below.

Adam Martinson, Construction Supervisor - 651-247-2273 Tanner Bakke, Construction Supervisor - 320-367-4537

Dan Boyum, City Engineer - 651-604-4829



City of Maple Plain
5050 Independence St.
PO Box 97
Maple Plain, MN 55359
763-479-0515
www.mapleplain.com 



Manage Newsletter Preferences