Happy Friday! Here's your weekly construction update.

Howard Avenue and Independence Street:

Construction crews will be working on Saturday, October 13. We anticipate this will be from 7:00 a.m. to 5:00 p.m.

If you are planning on applying for a deferred assessment please contact Nicole or Bobby at City Hall- 763-479-0515.

Week of October 15th Schedule-

Monday (October 15)- The construction crew will be working on storm sewer north of Independence and sanitary sewer on Independence.

Tuesday (October 15) - Saturday (October 20) - Two construction crews will be on site. One crew will be working on sanitary sewer on Independence and the other crew will be road building on Howard Avenue. Please note during road building there will be no access to driveways during construction hours. At the end of each day access will be restored.


Parkview Road and Maple Ridge Drive:

We do not anticipate any work in the area this upcoming week.



Construction Contacts:

For any non-emergency type questions or concerns, please feel free to contact City Engineering staff using the information below.

Tanner Bakke, Construction Inspector - 320-267-4537

Dan Boyum, City Engineer - 651-604-4829